Part A' Of the self-construction trilogy, I wrote about the planning stage. If you haven't read Part A, I recommend doing this now. We are now moving on to part B of the project. Preparations for construction.

We finished the previous section with a paper outlining our future home in our hands. Some people might be able to take the plan and imagine it as a house. I was not blessed with this ability. I highly recommend asking the planners to also present a 3D diagram of the finished house so that if, like me, you can't imagine the house from the plan, you'll at least have an idea of what it will look like. There is also an option, for a fee, to order a simulation of the house as it will be after construction. Such a simulation can be done at several levels. These can be individual pictures of the house's interior and exterior as you choose. It could be a video of a tour of the house, and the most exciting thing is a simulation within a phone app. With this simulation, you can truly "wander" through the non-existent house. The price for preparing such a simulation as of July 2022 is about 10,000 shekels, but I assume this price will gradually decrease. I assume there is also an option for a more detailed simulation (with furniture) and a less detailed one.

Computer rendering of the house to be built
Examples of simulations from the company website Glances And with their approval

After the house design, a construction project management method must be chosen.

Three options for managing the construction project

  • Self-build – You hire professionals, sign contracts with them, and make sure to pay them. You can also integrate a construction supervisor into this method who will oversee the quality of construction by the professionals.
  • Prime contractor – You will conduct a tender among several contractors who received the plans and bill of quantities and select the contractor to carry out the construction. You will sign a contract with this contractor, including the price and payment terms until you receive the apartment key. In fact, this is somewhat similar to purchasing an apartment from a contractor in apartment construction, except for a bank guarantee (lending bank), which is not customary in building a single house as opposed to an apartment building.
  • Project manager Also sometimes called a construction supervisor – in this method, you choose a project manager who is responsible for tendering professionals for each stage of construction (framing, electrical, plumbing, air conditioning, aluminum (windows), etc.). You pay a salary to the project manager, who is responsible for managing the execution personnel and the quality of work, and at the same time, you pay each professional according to their work.

Advantages and disadvantages of each method

Self-build

You have a house plan in hand and are starting to call various contractors to have them build each stage of the house. In my opinion, this approach is only suitable for those with construction experience who know suppliers of raw materials and contractors. If you fit this description and might even build part of the house yourself, then there’s a chance you’ll be able to reduce construction costs. In my opinion, the chances are slim, and assuming you have some knowledge but construction isn’t your profession, this is a very risky alternative—financially, in terms of work quality, and in terms of timelines. But yes, there is a chance to save about 15% that a project manager or general contractor would have cost.

Prime contractor

You have plans and a bill of quantities that detail everything that will be in your house. You contact several contractors, give them the plans, meet with them, and receive a quote for execution. At this stage, you choose the contractor that you believe is the most suitable in terms of quality versus execution. I highly recommend including personal chemistry in your considerations as well. You will be spending quite a bit of time together, even if it seems to you that your role is only to transfer money and wait for the house. I highly recommend that the designer also be a partner in choosing the contractor. The designer will also need to work with the contractor to ensure that the design is accurately executed. Furthermore, it is likely that the designer has more construction experience than you, so their opinion and impression are important. Another point worth considering is hiring a construction supervisor to act as a 'guard for the guards." Someone who is not affiliated with the contractor and ensures the quality of construction. With this method, you should have more peace of mind. Your role, so to speak, is only to pay the contractor according to the construction progress and to choose flooring, toilets, etc. Various risks, such as the rising cost of building materials, are supposed to be borne by the contractor, and to do so, they will naturally price the construction slightly higher than the other two methods from the outset. Sometimes the contractor will also link payments Construction input index. In any case, in self-build construction there is no bank accompaniment, so under no circumstances, no matter how much you fear indexation, should you make advance payments or pay for things that have not been done.

Project Manager / Construction Supervisor

In this method we have chosen, we hire a project manager who also serves as the construction supervisor. The project manager is responsible for conducting tenders or selecting, through any other method, the appropriate professionals for each stage of construction (framing, plastering, flooring, electrical, air conditioning, plumbing, etc.) and the appropriate building material suppliers for each stage (steel, concrete, aluminum windows, etc.). The project manager is paid by us based on the contract we signed with them. When they select professionals and they carry out the work, we pay them according to milestones set by the project manager. The responsibility for the quality of construction lies with the project manager, who should possess (at least) three important qualities:

  1. Construction experience Or extensive knowledge in construction. For example, a former contractor, a practical engineer, or a construction engineer.
  2. Good acquaintance with professionals and suppliers in the area where the house is being built.
  3. Management ability.

Let's pause for a moment on the topic of management capability. The issue of management capability is not trivial at all. A deep understanding of construction processes and seizing opportunities can be invaluable, both financially and in terms of time. An average project manager will manage construction as a linear process with a fixed order of operations, resulting in a house. A good project manager will know how to seize opportunities and perform tasks concurrently, even if it sometimes appears illogical from the outside. Two examples from our home:

  1. A little after they poured the top floor ceiling and before they did the interior and exterior plastering, I saw the seven air conditioner units on the skeleton roof. I asked the project manager for an explanation, and he replied: I ordered a crane truck to erect a few block platforms upstairs. There was space left on the truck. Instead of ordering a crane later specifically for the air conditioners and paying for additional transport, I combined the transports, and in general, air conditioners can be bought cheaper in winter than in summer, when we will finish construction.
  2. They haven't even finished the foundation yet, and there was already a huge pile of garden soil in the yard to be spread in the garden after construction is completed (the house itself sits more or less on limestone). I again asked what the deal was, and the answer was that on another project, it was necessary to excavate and remove excellent soil. Instead of paying for removal on the second project which was further away, and then paying us for the purchase and transport of soil, a win-win combination was made between the two projects of the same manager.

How to choose a project manager? Like any professional who on one hand costs a lot of money and on the other hand has great responsibility, the choice is not simple. Those who are not involved in construction find it difficult to judge the quality of work. What you can do is ask to speak with previous clients and ask them about a few topics:

  1. Were they satisfied with the communication style and construction style? Different people have different ways of communicating, and construction is a year-long project full of passions. The project manager may also find themselves acting as a marriage counselor.
  2. Are they satisfied with the final product, the house?
  3. Are the engineer and the architect satisfied with the construction process and the construction results?
  4. Did you stay within the construction budget? If not, do you know why?

managed our construction Ronen Kolan Tel: 053-340-6115. I recommend looking into this before starting construction in the North. In the next chapter, I will write about the desired relationship in the client-planner-project manager triangle, about making decisions on construction methods, and about the start of the construction process.

View from our living room
Construction Progress – Partial Flooring

Note, the term self-build was mentioned above as a form of managing the construction project itself. This might be confusing because in terms of a mortgage or taxation, it doesn't matter how you choose to build; it will still be defined as "self-build.".

Beyond Part III – Construction Methods


On Wednesday, December 28, 2022, at 8:00 PM, I will be hosting a Zoom conference on economic growth. The conference is branded as being for young people because it is based on my presentation to soldiers. I have no doubt that the insights I will share will benefit everyone (and especially young people, as rules for economic growth are best learned as early as possible). I think this could also be a great opportunity for parents to engage with economic content together with their teenagers. According to feedback from the soldiers, the lecture was delivered with humor, which definitely helped in digesting the important economic topics. Click here now for more details and registration.


As always, I'd be happy to receive any feedback. The best place is in the comments section below. You can also reach me on any matter via email at rimon@effm.co.il or by phone at 054-5232-799.

Click here to enter my YouTube channel

Click here for the Facebook group "Growing Financially" Together there, we are engaged in... economic growth.


10 תגובות על “יומן בניה עצמית של בית פרטי – חלק ב'

  1. Just so you know, a company from the Baltic States called Planner 5D allows you to design your home yourself. If you need assistance, such as a 3D visualization, the price is $100 for a house up to 100 square meters and $150 for a house up to 200 square meters. You will receive a 3D computer visualization with the help of a designer. This also includes a 2D floor plan of the house. This leaves you with a lot of change from 10,000 NIS. I did this this week and the result is amazing.

    1. Hey Reuven. Thank you so much. I love that community members expand knowledge even further than I have. I didn't even think to check the possibility of doing it abroad.
      Thank you for the additional information.
      Indirectly, I understand that you are continuing to progress. Well done and much success.

  2. Hi Rimon, how are you? Congratulations on building the house. There's no doubt it's an amazing experience, especially when everything works as it should...
    Regarding house renderings, there's a website for freelancers from all over the world where you can choose a designer. You pay them per rendering, and you can get a finished 3D rendering of excellent quality for a few hundred shekels. We bought a plot and decided to build it ourselves, of course with a construction supervisor. We did our homework and checked with several general contractors. There are advantages and disadvantages. Advantages: there's a warranty on the construction, and you don't have to deal with bureaucracy and nerves with the tradespeople; all dealings are with the contractor. The disadvantages are that any change you want to make will cost you money, unlike self-building. You are limited by the technical specifications, and any change will cost money. After we finished the construction, the price for self-building was significantly cheaper by several hundred thousand shekels compared to building with a general contractor. Regarding the air conditioner units ☺️ every stage has its time, and looking to save a few "cents" relative to the total construction cost is a bit problematic. It's not clear if the roof has been waterproofed or plastered yet, as it only causes problems. You can buy the air conditioners in the winter and enjoy a 'discounted' price, and request delivery for the time you need. A crane costs 300 shekels per hour, and that's the end of it ☺️ Anyway, it looks amazing, and I'm happy for you. It's definitely an experience, and if everything works like clockwork, your appetite for building will only grow. 😀 Happy holiday, Rimon. And I'm always happy to read and learn from your emails and videos.

    1. Dear Itzik,
      Thank you very much for the thoughtful response. I have no doubt it will benefit others. How
      It's fun to get additional knowledge from the audience.
      We are also considering the option of a project manager – self-build.
      Regarding the air conditioners – that's just one example that came to mind because it seemed so unusual. I live far away
      From the construction site, I only see her once a week. Other examples include, for instance, judicious use of rental time for a dumpster.
      And more and more.
      Thanks again and happy holidays.

  3. Hello Pomegranate
    It was a pleasure to read your article.
    We are also in the process of building a house in the north, now we are just submitting for the permit.
    I wanted to ask, perhaps from your experience, how can one know how to divide the construction budget?
    So, let's say our goal is for the construction to be up to 2 million NIS. How do I know what percentage of that I need to allocate to the frame, what percentage to windows, what percentage to plumbing and electricity, what percentage to the kitchen and furnishings, and so on...
    In other words, how can the overall budget be used to define the target budget for each section?
    Thank you!

    1. Thank you very much, my son,
      You shouldn't do it yourself.
      If you chose a turnkey contractor, the payment schedule according to the contract is more or less fixed.
      It will show you how much each step costs.
      If you chose a project manager, they should take the plans and the bill of quantities.
      that the planners prepared and to turn the specifications into prices.
      This way, you know not only how much the frame costs, but also how much the iron in the frame costs.,
      The blocks in the frame, the concrete, etc. Good luck!.

      1. Yes, but according to this, I'm essentially led by their pricing, and thus I won't really be able to know where I need to save and where I can increase, or exceed at the expense of something else.

        1. Hello son, in my opinion, your responsibility is to choose the best and most suitable professionals for you in terms of communication and reliability. From that moment on, you are in their hands, just as you are in the hands of a pilot on a passenger plane. Even if you know that the structural frame is a third of the cost, it's not my preference to help you know whether to save on the frame or not on the one hand, and what the consequences of saving are. It's completely clear that different types of blocks and different types of plaster or any other building component are priced differently. The connection between the price and the consequences is provided to you by the professionals so that you can choose. In our case, I primarily placed trust. As someone who makes a living selling knowledge, I try to acquire knowledge from others. A sentence like "mineral plaster is better even though it's more expensive because it's important for the house to "breathe"" seems like Chinese to me. Or whether I trust the architect who says it's really worth investing money in this particular aspect, or whether I don't trust her. The same goes for insulating blocks, double glazing, and a thousand and one other things.

  4. Pomegranate hello,

    Thank you for sharing the construction log.

    I noticed in the picture that there is partial flooring, and if I'm not mistaken, I see that the flooring is applied directly to some surface (perhaps a concrete slab or a rough concrete mix). I would be happy to hear what this method is.
    I am familiar with casting, mortar plastering, and flooring.

    Congratulations on your new home.

    1. Thank you very much, Ilan.
      I don't think my superpower is construction methods, etc. In my opinion, a good advisor should mainly say when they don't know something. After this introduction, my working method has been to hire people I trust and give them autonomy to implement things as they see fit. Or in other words, tiling is not my expertise and it's better to ask others. There is no problem if you present the situation to them.
      In response to your question, the project manager said that they are using lightweight concrete and then tiling over it. They used a similar method before pouring the ground floor slab.
      On the styrofoam layer (insulation between the ground and the floor) and the steel mesh, they poured a thin layer of lightweight concrete that cannot bear weight other than the weight of workers walking on it without fear of piercing the styrofoam itself. I hope I haven't confused the order of layers in the explanation.